Recent work
Work carried out on operating sites, described in enough detail to be useful. Breakdowns, shutdowns, controls and installation work across manufacturing and food production.
Food production
A failed communications port left the HMI with no control. The replacement needed its firmware brought up to revision and the project reconfigured before the existing program would load.
Goodman Fielder, Burleigh Heads · 2025
Food production
Document, label, disconnect, replace and recommission, all inside a 24-hour shutdown window on a crate robot.
Goodman Fielder, Burleigh Heads · 2026
Food production
A legacy switchboard with drawings that no longer matched the installation, and a fuse mounted out of sight behind an output module.
Goodman Fielder, Burleigh Heads · 2025
Brick manufacturing
Two transformer stacks built and installed, supplies re-routed and screens recommissioned during an annual four-week shutdown.
PGH Bricks and Pavers, Oxley · 2025
Work is published here where the client is happy for it to be. Some jobs appear without the client named, and some do not appear at all.
Get in touch
If something has stopped, ring us. It is faster than a form and gives us the best chance to understand what is happening on site straight away.
0434 059 952For breakdowns and after-hours requirements, call to check current availability.
Commercial and industrial sites only. We do not do domestic or residential work.